SIGN UP MEMBER LOGIN:    
ARTICLE

Share Point Designer Work Flow: Part IV

Posted by Destin joy Articles | SharePoint August 26, 2010
In this article I am explaining, how to update a list item using share point designer.
Reader Level:

HTML clipboard

In this article I am explaining, how to update a list item using share point designer.

1. This is my list say Task List.

  Image1.gif

2. Here I am updating the list Item % complete to 100 ,if the Status is completed while editing or adding event . item.

1. First of all you have to open your web application in share point designer

  Image2.gif

2. You have to go to File -> New -> Work Flow as shown below

  Image3.gif

3. From the next screen, You have to give a name for your work flow.

4. Select the List where you want to incorporate the work flow from the second drop down as shown below

5. Select automatically start this work flow when new item is added or changed.

Image4.gif
 
6. Click Next

7. From the next screen Select Condition then Compare Task Field

Image5.gif


Image6.gif
 
8. From the next screen, select the field you want to compare .I selected Status the value you set as completed

Image7.gif

9. Then Click on Actions Then select Update List Item

Image8.gif

10.
From the next screen click "This List" then select Current item from the List drop down

Image9.gif

11.
Click on Add button Select Set Field value as " % complete" To This Value as 100.

12. Click OK and Finish .You are done

Image10.gif


13. You can see in the above screen .I didn't filled the value for % complete but I made the status as completed.

14. In the below screen you can see it is updated with 100%

Image11.gif

Login to add your contents and source code to this article
share this article :
post comment
 
Team Foundation Server Hosting
Become a Sponsor
PREMIUM SPONSORS
  • Finally – a virtual platform that delivers next-generation Windows Server 2008 Hyper-V virtualization technology from a managed hosting partner you can truly depend on. Visit www.maximumasp.com/max for a FREE 30 day trial. Hurry offer ends soon. Climb aboard the MaxV platform and take advantage of High Availability, Intelligent Monitoring, Recurrent Backups, and Scalability – with no hassle or hidden fees. As a managed hosting partner focused solely on Microsoft technologies since 2000, MaximumASP is uniquely qualified to provide the superior support that our business is built on. Unparalleled expertise with Microsoft technologies lead to working directly with Microsoft as first to offer IIS 7 and SQL 2008 betas in a hosted environment; partnering in the Go Live Program for Hyper-V; and product co-launches built on WS 2008 with Hyper-V technology.
    Finally – a virtual platform that delivers next-generation Windows Server 2008 Hyper-V virtualization technology from a managed hosting partner you can truly depend on. Visit www.maximumasp.com/max for a FREE 30 day trial. Hurry offer ends soon. Climb aboard the MaxV platform and take advantage of High Availability, Intelligent Monitoring, Recurrent Backups, and Scalability – with no hassle or hidden fees. As a managed hosting partner focused solely on Microsoft technologies since 2000, MaximumASP is uniquely qualified to provide the superior support that our business is built on. Unparalleled expertise with Microsoft technologies lead to working directly with Microsoft as first to offer IIS 7 and SQL 2008 betas in a hosted environment; partnering in the Go Live Program for Hyper-V; and product co-launches built on WS 2008 with Hyper-V technology.
Become a Sponsor