This is a short and sweet FAQ which iterates through the most common metrics which will help you judge your project health.
We have been developing lot of videos for project managers and architects , you can see all my videos at http://www.questpond.com/ , do let me know your feedbacks.
Can you explain PV, AC and EV?
PV (Planned Value):- PV is also termed as (BCWS) Budgeted cost of work scheduled. It answers "How much do we plan to spend till this date?". It's the total budgeted cost for the project.
AC (Actual Cost):- AC is also termed as ACWP (Actual cost of Work Scheduled). It answers "How much have we actually spent?".
EV (Earned Value):- EV is also termed as BCWP (Budgeted Cost of Work Performed). It answers "How much work has actually been completed?".
Figure: - PV, AC and EV
Many project managers traditionally use only Actual and Planned values. But it's very much possible that you will not get proper results from the same. For instance consider the project shown in figure 'Actual and Planned'. The project duration is 5 weeks. According to the planned value graph in Week1 we will spend 600$, in week3 we will spend 3800 $ and on the completion of project it is 6000$.
But we where getting computers at a discounted cost in Week1 itself so we bought the computer. According to plan we are supposed to spend in Week1 750 $ but in actual we have spent 3000$. By comparing with the actual plan value we have concluded that we over budget by 2250 $ in the first week. But that's not the actual case; in reality we bought the computers on discounted rate. So the graph is showing something really wrong. This issue is solved by using EV (Earned Value).

Figure: - Actual and Planned
Earned Value measures progress and gives us forecasting, thus giving us an actual measure of the health of the project. For instance see the figure 'Earned Value'. We have given two views one is the planned value and the other is the earned value. According to the planned value it's a four week project with 25% (2500 $) work completed on Week1, 50 % (5000$) work completed on Week2 and so on. Now when the project starts executing on Week1 only 20% work is completed which means we have spent 2000$ and on week2 only 30 % work is completed. 2000$ and 3000$ shows the earned value for Week1 and Week2.
Figure: - Earned Value
Can you explain BCWS, ACWS and BCWP?
Please refer the above question.
What are the derived metrics from Earned Value?
Earned Value gives us three metric views for a project.
Figure: - Earned Value Metrics
Current Progress: - This shows how we are performing in the project.
Forecasting: - Will help us answer how we will do in the project in future.
How will we catch up: - In case the project is moving behind schedule or over budget how do we make up?
Current Progress metrics
Schedule Variance (SV)
Schedule variance is the difference between Earned value and planned value
|
SV = EV - PV |
|
SV = EV - PV |
|
CV |
Description |
|
0 |
You are on right on budget. |
|
Negative |
You are over budget. |
|
Positive |
you are under budget. |
Cost Variance (CV)
Cost variance is the difference between earned value and the actual cost.
|
CV = EV - A |
|
CV = EV - AC |
|
CPI |
Description |
|
1 |
You are right on budget. |
|
Less than 1 |
You are over budget. |
|
Greater than 1 |
you are under budget. |
Cost performance Index (CPI)
CPI is the ratio of Earned value to Actual cost.
|
CPI = EV / AC |
|
CPI = EV / AC |
|
SPI |
Description |
|
1 |
You are right on schedule. |
|
Less than 1 |
You are behind schedule. |
|
Greater than 1 |
you are ahead of schedule. |